Sydney Kingsford Smith Airport - Project Overview
Security Screening & Pier B Bussing Upgrades
 Client: Johnson Controls
Completion Status: Completed 2025
​
Integrata delivered two concurrent BMS and HVAC controls projects within operational areas of Sydney International Airport in partnership with Johnson Controls — both completed in 2025. Works spanned the T1 Main Screening Security Upgrade and the Pier B Bussing mechanical systems upgrade, with the majority of works undertaken after-hours by security-cleared personnel under strict operational staging and access requirements.
Â
T1 Main Screening Security Upgrade:
The T1 scope involved BMS installation and controls infrastructure works associated with HVAC systems serving critical airport screening environments.
-
New BMS control panels, enclosures, and Johnson Controls network control engines
-
BACnet MSTP communications infrastructure and control cabling
-
Integration of HVAC mechanical plant and field devices including zone temperature sensors, differential pressure switches, duct static pressure transmitters, and current switches
-
Point-to-point testing and commissioning support within occupied operational spaces and curfew zones
Â
Pier B Bussing BMS Upgrade:
The Pier B scope involved a Johnson Controls Metasys BMS deployment across multiple air handling systems and mechanical plant serving airport bussing and passenger movement infrastructure.
-
BMS installation and integration across AHU-1 through AHU-12, FCU systems, lift ventilation, exhaust fans, and VSD-controlled mechanical plant
-
Johnson Controls Metasys platform with BACnet MSTP field controllers integrated to supervisory controllers and third-party systems
-
BACnet/IP, Modbus, Schneider CRAC, and Mitsubishi HLI integrations
-
Field device installation including duct COâ‚‚ sensors, humidity transmitters, differential pressure switches, temperature sensors, Belimo valve and damper actuators, and fan status monitoring devices
-
MSSB mechanical interfaces and VSD speed control systems
-
COâ‚‚, differential pressure, and temperature and humidity monitoring throughout
Â
Both projects were coordinated closely with airport operations teams across overlapping delivery programmes within live, security-controlled passenger environments.